Guided project path
Build with the same professional lifecycle
This guide is not a separate course taxonomy. Clients, self-builders, and fresh graduates follow the same 14 phases used by live projects, with the expected output and approval gate visible at every step.
- 1
Intake / Interview
- Output
- Client brief, constraints and decision owners
- Gate
- Client confirms the brief and decision owners.
Interview before drawing: users, rooms, priorities, budget range, timing and non-negotiables.
- 2
Site / Location Discovery & Survey
- Output
- Measured site record, photos and risks
- Gate
- Survey record is reviewed and missing measurements are resolved.
Verify dimensions, access, utilities, orientation, neighbours, existing conditions and site constraints.
- 3
Scope / Feasibility
- Output
- Agreed scope, assumptions and feasibility note
- Gate
- Client and consultant accept scope, exclusions and key assumptions.
Translate the brief and survey into what is feasible before promising cost or schedule.
- 4
Tender / Appointment
- Output
- Appointment decision, proposal or signed scope
- Gate
- The responsible consultant or delivery team is formally appointed.
Compare scope, deliverables, exclusions, fee structure, schedule and responsibilities—not price alone.
- 5
Concept & Moodboard
- Output
- Selected design direction and moodboard decision
- Gate
- Client records one approved direction or requests revision.
Use moodboards to decide atmosphere, material language and references before detailed modelling.
- 6
Design Development
- Output
- Coordinated plans, elevations, material and system decisions
- Gate
- Design package is coordinated enough to detail and cost.
Resolve layout, ergonomics, lighting, MEP interfaces, material transitions and buildability.
- 7
Detail Drawings + BOQ / Budget
- Output
- Issue drawings, specifications and cost plan
- Gate
- Drawings and BOQ share one approved revision and budget basis.
Do not price from moodboards. Quantities, specifications and drawing revisions must agree.
- 8
Permits / Procurement
- Output
- Permit status, vendor comparisons and purchase plan
- Gate
- Required approvals and long-lead procurement are cleared for mobilisation.
Track permits, samples, lead times, alternates, quote validity and who owns each purchase.
- 9
Site Preparation
- Output
- Mobilisation checklist and site readiness record
- Gate
- Site access, safety, protection, utilities and working area are ready.
A clean mobilisation prevents early rework: protect existing finishes, confirm storage and define site rules.
- 10
Construction
- Output
- Progress records, site logs, RFIs and change orders
- Gate
- Planned works are substantially complete and open changes are controlled.
Use daily evidence, clear assignments and formal change orders instead of decisions disappearing in chat.
- 11
QA / Snag / Punch List
- Output
- Inspection record and closed defect list
- Gate
- Critical defects are closed and remaining items have owners and dates.
Inspect room by room and system by system; attach evidence to each issue and retest fixes.
- 12
Handover / Key Transfer
- Output
- Accepted handover pack, keys and asset information
- Gate
- Client accepts handover with documented exceptions.
Handover includes keys, manuals, warranties, as-built records, contacts and unresolved items—not only a ceremony.
- 13
Warranty & Maintenance
- Output
- Warranty register and maintenance schedule
- Gate
- Warranty owners, expiry dates and recurring maintenance are recorded.
Convert vendor warranties and care instructions into reminders the owner can actually follow.
- 14
Closeout
- Output
- Final archive, commercial closeout and retrospective
- Gate
- Final documents, outstanding obligations and lessons learned are complete.
Archive the record so the next renovation, maintenance visit or graduate team can understand what happened.